BIRATNAGAR — The rail yard built to unload freight trains at Biratnagar's Integrated Check Post has sunk and cracked within about three years of the cross-border cargo line opening, and cargo trains still do not arrive regularly, traders and officials said.
“Looking at the condition of the yard, it clearly needs immediate repairs,” said Umesh Shrestha, chief of the Biratnagar Customs Office. “It appears there may have been negligence during construction itself.”
The 18.1-kilometer line connecting Bathnaha in India to Katari in Morang was built by Indian company IRCON with a grant from the Indian government and was inaugurated in 2023. Trains currently run from Bathnaha to the check post in Biratnagar. The Nepal Customs Yard, built alongside the line, has been handed over to Nepal.
Cargo trains have reached Biratnagar only five times since the line opened, according to TransNepal Freight Services Pvt Ltd, the company contracted to operate the check post. It said the first arrived on June 20, 2026, followed by trains on Aug. 13, Sept. 10, Sept. 27 and Nov. 7.
Anil Kumar Sah, president of the Morang Merchants' Association, said the railway's potential has not been realized because the yards, platforms and roads have not improved.
“About one kilometre of the railway yard used to unload goods from trains is damaged,” Sah said. “The weight of heavy equipment [cranes] used to unload containers and move them from one place to another has caused the yard surface to sink and crack, with potholes forming in several places.”
Sah said asphalt had peeled off in some sections, making it difficult to operate heavy equipment and handle containers. Industrialists and traders allege the surface was laid without adequate groundwork and with poor-quality materials.
Mukesh Rathi, director of the private company operating the yard, said the facility also lacks a closed shed, which makes it impossible to import moisture-sensitive goods such as salt, sugar, chemical fertilizer and industrial chemicals by rail.
Traders say it remains unclear who will pay for repairs or which agency is responsible, since several government bodies and the operating company share management of the check post and yard.
Prakash Prasad Pokharel, chief executive officer of the state-owned Nepal Transit and Warehousing Company Limited, said his company is preparing a repair plan. “A budget of Rs300 million has been allocated, and we are planning to begin repairs soon,” he said during a discussion with business representatives.
Pokharel said technical studies would be completed by mid-December, with tenders to follow the next month, so that work can be finished within the current fiscal year.
A parliamentary committee recently inspected the check post and directed the agencies concerned to arrange repairs, but no work has started, Sah said. Finance Minister Swarnim Wagle also inspected the area on Friday.
Anil Sarada, senior vice president of the merchants' association, said repairs to the yard, platforms, storage areas and roads should be a priority alongside regular train services.
“If the infrastructure of the ICP, which was built to facilitate trade, continues to deteriorate, the plan to develop Biratnagar into a regional trade hub could also be undermined,” Sarada said.