Construction begins on 117-km MCC transmission line across five districts

The US$76.65 million Lapsiphedi-Ratmate-New Hetauda project will involve 303 transmission towers across five districts.

Inner Circle Nepal newsroom
Updated 3 min read
ShareWhatsAppFacebookXLinkedIn
Construction begins on 117-km MCC transmission line across five districts
Photograph: Shutterstock

Construction has begun on a 117-kilometre, 400-kilovolt electricity transmission line connecting Lapsiphedi in Kathmandu, Ratmate in Nuwakot and New Hetauda in Makwanpur under the Millennium Challenge Corporation (MCC) Nepal Compact.

The Millennium Challenge Account Nepal (MCA-Nepal) started construction work in Sindhupalchok district this week, marking the beginning of physical work on the transmission line, which will extend across Kathmandu, Sindhupalchok, Nuwakot, Dhading and Makwanpur.

According to MCA-Nepal, the project will require approximately 303 transmission towers and will operate as a double-circuit 400 kV line. The infrastructure is designed to connect the three substations and strengthen electricity transmission capacity across central Nepal.

A major section of Nepal's wider electricity network

The Lapsiphedi-Ratmate-New Hetauda section represents approximately 37% of the 315-kilometre transmission network being developed under the MCC Nepal Compact.

The wider Electricity Transmission Project consists of three major inland sections: Lapsiphedi-Ratmate-New Hetauda, Ratmate-New Damauli and New Damauli-New Butwal. An additional 18-kilometre section connects the New Butwal substation to the Nepal-India border.

The wider network is intended to reduce transmission bottlenecks, improve electricity reliability and strengthen Nepal's ability to participate in regional electricity markets.

The 400 kV rating refers to the voltage capacity of the transmission line, while its double-circuit design allows two electrical circuits to operate along the same transmission corridor. This enables greater power-transfer capacity compared with a single-circuit arrangement.

For Nepal, expanding transmission infrastructure is particularly important as electricity generation capacity grows.

Without adequate transmission lines, electricity produced by hydropower projects can face limitations in reaching major consumption centres and the wider national grid.

Contract signed in 2025, construction begins in 2026

Although construction has only recently started, the contract for this transmission line was awarded much earlier. MCA-Nepal signed an agreement with Ashish-Bozlar JV on September 26, 2025, for the design, construction, installation, testing and commissioning of the 117-kilometre section.

The contract was valued at approximately US$76.65 million, excluding applicable taxes, and carries a completion period of 42 months from the formal commencement date.

MCA-Nepal's March 2026 progress report had recorded that the detailed design for the Lapsiphedi-Ratmate-New Hetauda section had been submitted for review. The latest construction start therefore marks a new stage following the earlier contracting and design process.

Land acquisition and compensation remain important

Beyond engineering and construction, the project's progress will also depend on how land-related issues are managed along the transmission corridor.

Installing hundreds of towers requires land for tower foundations, access routes and associated infrastructure. Transmission lines also create right-of-way restrictions, which can affect how landowners use property beneath or near the lines.

MCA-Nepal's environmental and social safeguards framework provides for Resettlement Action Plans covering permanently acquired land and restrictions on land use within transmission-line corridors. These plans are intended to address compensation, physical and economic displacement, community consultation and livelihood restoration.

The framework specifically includes a resettlement package for the section connecting New Hetauda through Ratmate to Lapsiphedi.

However, the latest construction announcement does not provide a breakdown of the number of affected landowners, compensation payments completed, unresolved land disputes or the status of access to all proposed tower locations.

These details will be important in determining whether construction can proceed according to schedule without prolonged disputes with affected communities.

Implications for Nepal's energy trade

The transmission project is also connected to Nepal's longer-term ambition to expand electricity trade with neighbouring countries.

The wider MCC electricity network is designed to strengthen domestic transmission capacity while improving connections between major electricity substations. Its completion could help Nepal move more electricity across the national grid and support greater participation in regional power markets.

However, the construction of this 117-kilometre section alone does not establish that additional electricity exports can immediately take place. Effective transmission will also depend on the completion and operation of connected substations, other transmission corridors and cross-border infrastructure.

With construction now underway, attention will turn to whether the project can meet its contractual timeline, manage land-related concerns and deliver the transmission capacity expected from the wider MCC investment.

ShareWhatsAppFacebookXLinkedIn

Spotted an error? Tell the desk — we publish corrections openly, and you can read our corrections policy.

Keep reading nepal coverage

The weekday briefing — one email each morning, Nepal time. Free, and unsubscribe in a click.

Related reading

More →