Seven years after construction began, Nepal’s new Federal Parliament complex at Singha Durbar cannot yet host Parliament. Officials say the House of Representatives chamber is built, but its audio, video and conference systems have not been tested and it has not been formally handed over to the Federal Parliament Secretariat.
Ekram Giri, joint secretary and spokesperson of the Secretariat, said the entrance to the chamber is still under construction. The Secretariat is aiming to move in by the end of November but is not sure it can. The National Assembly chamber is unfinished, with interior and other work continuing across the complex.
Roshan Shrestha, chief of the Special Building Construction Project, put overall progress at 95 percent. He blamed recent delays on reduced work during Dashain and Tihar, border disruptions and late supply of interior fittings from China. Dilip Bhandari, director general of the Department of Urban Development and Building Construction, said the government plans to complete all work by mid-January 2027, and said some delay arose because the interior contract was awarded after the main construction contract.
From three years to seven
Then prime minister KP Sharma Oli laid the foundation stone on Sept 18, 2019. The main construction agreement with Tundi-SHEC Joint Venture was signed on Oct 3, 2019, with a three-year deadline of October 2022 so that the Parliament elected in 2022 could sit in the new building. The complex covers 156 ropani at Putali Bagaicha in Singha Durbar.
The deadline has since been extended to April 2023, October 2023, April 2024, March 2025, December 2025 and now February 2027, six extensions in all. February 2027 is more than four years beyond the original date. A seventh extension was sought, with the contractor applying in August, but the latest approved deadline is February 2027.
The money
The main contract was Rs 5.67 billion. Project officials earlier said variation orders, design changes, adjustments to lump-sum work and additional structures raised the cost of civil construction to about Rs 6.29 billion. A separate interior contract worth Rs 2.35 billion went to KC-Shyamsundar-Baniya JV on July 2, 2023, covering furniture, decoration, IT, sound systems and hardware and software.
Its deadline was mid-July 2024 and has been extended four times, to mid-May 2027. A Rs 37.9 million roofing contract, awarded to Chainlink Engineering Company on March 10, 2024, is also incomplete, with a deadline of mid-May 2027.
The original contract values total about Rs 8.06 billion, or about Rs 8.68 billion with the revised civil cost.
Why it stalled
The interior contract was signed after the main deadline had passed, nearly four years after the main contract. A parliamentary chamber depends on microphones, audio and video distribution, conference systems and IT, so a finished structure does not make a usable chamber.
In August 2025, a parliamentary committee inspected the site, and lawmakers said finishing work was only 5 percent complete and that two more years might be needed. Project director Sunil Kumar Thakur said civil work was done and the rest could be finished in the revised time. Later deadlines were then missed.
Penalties and procurement
In July 2026, the government introduced the Public Procurement (Fifteenth Amendment) Regulations, 2083, a mechanism for unfinished contracts with at least 50 percent physical progress. It covers cases such as government suspension of work, missing budget, payment delays and recognised compensation events. It also says liquidated damages are not collected for the period of an extension granted under it.
Rabindra Bohora, then director general, said in July that the government was preparing to penalise contractors for repeatedly missing deadlines and that recent delay came mainly from weak contractor management, though the amended rules allowed further extensions.
What it costs Parliament
The complex has 12 buildings, including both chambers, committee buildings, a library, a museum, party offices, the Secretariat and parking for 476 four-wheelers and 800 two-wheelers. Parliament has 275 House members, 59 National Assembly members and 16 committees. The House sits in a multipurpose hall and the National Assembly in an old Agriculture Committee hall, which limits space, technical infrastructure and committee scheduling. Speakers and committees have repeatedly urged faster work.
What is next
The Secretariat has not said whether it will refuse handover if systems fail testing.The main contract deadline is February 2027, and the interior and roofing contracts run to mid-May 2027.