The parliamentary Public Accounts Committee on Tuesday directed the government to submit all documents related to the cancellation of the main construction tender for the Sunkoshi-Marin Diversion Multipurpose Project within seven days.
Committee chairman Bharat Bahadur Khadka issued the directive after discussions with Dinesh Rajauria, director general of the Department of Water Resources and Irrigation, and officials of the Ministry of Energy, Water Resources and Irrigation.
The committee took up the matter after a complaint alleging that the tender for the project's headworks, dam, powerhouse and associated structures was cancelled at an advanced stage, after major bidding procedures were complete. The complainant has questioned the legality of the decision and warned of possible financial losses to the state.
Rajauria told the committee the cancellation was needed to comply with the 16th amendment to the Public Procurement Regulations, 2064. He said the amended rules require a rated-point evaluation system for complex construction projects worth more than Rs 1.5 billion. That system assesses contractors on technical capacity, past experience and performance, not mainly on price.
Six companies took part in the international bidding, and three passed the technical evaluation. The tender was cancelled before their financial proposals were opened. Rajauria said restarting the process would ensure legal compliance, fair competition and the selection of a capable contractor. That is the department's justification, not a finding by the committee.
The project would divert water from the Sunkoshi River through a 13.3-kilometre tunnel to the Marin River. It is meant to irrigate about 180,000 bighas of farmland across parts of Bara, Rautahat, Sarlahi, Mahottari and Dhanusha, and to generate about 28 MW of electricity. The tunnel breakthrough has been achieved, but the headworks and other structures must still be built before it can operate.