Nepal weighs stricter hydropower IPO rules: Protecting investors or restricting investment?

The government is considering amending the Securities Act so hydropower companies must show at least 50 percent certified physical construction before issuing shares to the public.

Inner Circle Nepal newsroom
Updated 4 min read
ShareWhatsAppFacebookXLinkedIn
Nepal weighs stricter hydropower IPO rules: Protecting investors or restricting investment?

The government is considering a rule that would require hydropower projects to complete at least 50% of their physical construction, certified independently, before the companies behind them can issue initial public offerings (IPOs). It would not require electricity generation to have begun.

The proposal is in a draft Ordinance to Amend Some Nepal Acts Related to Investment and Infrastructure, 2026, which would amend the Securities Act, 2063. It remains a draft. The government has not decided whether to bring it as an ordinance or as a bill in Parliament, so no new restriction is in force.

What the draft says

A company would need certification of its construction progress from an independent, qualified technical evaluator. An IPO application could not be rejected merely because a project has not started commercial generation, as long as the certified progress and other conditions are met.

The prospectus would have to disclose:

• the total estimated project cost, the work remaining, the additional investment required and whether the financing to complete the project is secured;

• current construction progress, possible delays, cost escalation, major construction risks and expected completion dates;

• the status of power purchase agreements, generation licences and other approvals;

• a plan for using the IPO proceeds, with the money restricted to the approved purposes of the project;

• the estimated date of commercial production and the work remaining before operation.

Not a new threshold

The 50% figure already exists. Section 4(5) of the Electricity Regulatory Commission’s directive on prior approval and regulation of public share issuance by electricity companies requires hydropower projects under construction to reach at least 50 percent physical progress before issuing public shares. It sits in a directive, not in the Securities Act, and the proposal would give it statutory footing. A regulator can revise a directive, while changing an Act needs legislation.

Why the government is acting

Many hydropower companies have raised money from ordinary investors, and projects can run for years before earning revenue. Delays can come from difficult terrain, landslides and floods, permits, land acquisition, material shortages, financing problems and late transmission lines.

A study committee coordinated by former Securities Board director Phanindra Gautam examined the shareholding structure of listed hydropower companies. It found that some had gone years without paying dividends, that actual financial performance fell short of IPO projections, and that project costs rose. It also found that converting a large share of promoter holdings into ordinary shares right after the lock-in period had caused operational difficulties for some companies. Promoter shares cannot be freely sold during the lock-in. The findings strengthened the case for tighter eligibility.

The proposal also follows separate draft General Eligibility Guidelines for Public Issuance, 2026 from the Securities Board of Nepal (SEBON). One proposal would require a net worth of at least Rs 100 per share for companies issuing shares at a Rs 100 face value. The Independent Power Producers’ Association, Nepal (IPPAN) argued this would unfairly hit hydropower companies during construction, when their books do not yet reflect the value of the project. The government’s draft then set a separate pathway for under-construction projects, with the 50% certified threshold.

Where the debate lies

Investors want stronger protection. Share investor Keshav Koirala argued that a 50 percent threshold still exposes the market to risk and that hydropower companies should issue shares only after generation begins, since construction progress does not guarantee revenue or dividends.

Developers say they need public money earlier. Ganesh Karki, former IPPAN president, said developers need substantial capital in the early stages and that restricting IPO financing then would be inappropriate. He suggested stronger monitoring of construction and protection of investors’ money after approval.

Analyst Subas Chandra Dhungana questioned a single threshold for every project. He said large projects take years, and requiring them to finish the remaining half after approval could raise costs and delay operation. He suggested considering generation capacity, expected commercial production date and project characteristics.

In September, IPPAN president Mohan Kumar Dangi objected to provisions in SEBON’s draft. IPPAN asked to permit IPO applications at about 65 percent physical progress, to have a separate hydropower checklist, to drop the minimum net-worth requirement and SEBON approval of debt-to-equity ratios for project-based companies, to limit fit-and-proper tests to directors and management, to protect companies that had already applied, and to allow a transition period. It claimed the net-worth rule could stop about 60 percent of hydropower projects from issuing shares.

Who gains and who risks

Investors would get better information about construction, outstanding costs and financing. But a project at 50 percent can still fail on finances, technology, environment or grid connection, so the threshold does not make an IPO safe. Developers face added compliance costs, and smaller companies may struggle to pay for independent assessments, though eligible ones could raise public capital before generating power. A rule that is too strict could slow financing for a sector Nepal needs, and one that is too loose could expose small investors to weak projects.

What is next

The government has not said which route it will take or when. SEBON has not said how it would verify the 50% figure independently, whether the rules would apply to IPO applications already submitted, or how it would monitor money raised. Data on how many hydropower companies issued IPOs before generating power, and how many pay dividends, has not been published.

The central question is unresolved: if a company can raise money from the public after completing half its construction, who guarantees the other half will be completed, and who bears the loss if it is not? Neither the draft nor the officials so far have answered that.

Filed underEconomy
ShareWhatsAppFacebookXLinkedIn

Spotted an error? Tell the desk — we publish corrections openly, and you can read our corrections policy.

Keep reading nepse coverage

The weekday briefing — one email each morning, Nepal time. Free, and unsubscribe in a click.

Related reading

More →